WORKS: Security Street Lighting Upgrade

Client: Deakin University - Burwood Campus

daikin

Locate underground Services & confirm design practicality. Update as required to improve efficiency, safety & build ability through liaison with Deakin Project Supervisor

Supply and installation by trenching & boring or underground trunking conduits and cable pit network between distribution boards and lighting pole networks across 5 separate locations

Full reinstatement of footpaths & other surfaces affected by civil works

Supply & installation of appropriately sized trunking cables through each lighting system

Carry out Geo-tech surveys to ensure appropriate pole foundation design

Installation of foundations, lighting columns & outreaches outside normal working hours

Supply and installation of external pole mounted luminaires including remote control gear

Modifications to existing switchboards to incorporate new lighting circuits.

Supply and installation of Residual Current Devices in accordance with AS:3000.

Installation of photoelectric cell & manual bypass facility for lighting control where no existing security lighting system exists

Integration of new lighting to existing automated lighting control systems, where appropriate

Connect sub-circuit wiring, test & commission individual lighting systems

Supply and installation of cable identification markers, both concrete on surfaces and tapes in trenches.

Supply & Installation of SS conduit route markers throughout installed lighting systems

Provision of ‘As built’ Auto-cad drawings and operation and maintenance manuals.

Carry out works with minimal disruption to the University’s daily activities.