Emergency MSB Replacement
WORKS: Switchboard (MSB) & Group Meter Panel Replacement
Client: Vic Track - 124 Dynon Rd Kensington

Scope of Works
Provide Emergency Response To MSB Fire
Investigate options for Repair / Replacement
Provide Temporary Generator supplies for Industrial, Manufacturing & Retail Tenants
Remove burnt out switchboard, meter panels & sub-main cabling
Liaise with Citipower and Victrack to design new supply point location and arrangement for Group Metering and MSB that complies with current standards.
Design new combination group meter enclosure / MSB and engage switchboard manufacturer to construct as soon as practicable.
Install new 100Amp 3 phase supplies to existing tenants to current standards.
Liaise with Energy Retailers & Tenants to ensure prompt return of metering & supply.
Relocate existing 630A Consumers mains to new Group Meter position.
Install New Group Meter Panel / MSB, connect, Inspect & return supply to site
Isolate and decommission temparary supply services to tenants and cut over to new MSB
Complete & submit all Supply Authority, Statutory & required Retailer paperwork.
The Challenges
To respond immediately to emergency call.
Provide temporary tenant supplies, liaise with Supply Authority, design, construct, install & commission new Group Metering / MSB cubicle, re-cable tenant supplies, co-ordinate metering with Retailers & return permanent supply to tenants with negligible disruption to their businesses.
All tasks & processes completed to client’s complete satisfaction.